PMO Performance Dashboard

Inland Empire Utilities Agency · Last updated April 7, 2026

Schedule Health

SPI / CPI Performance & Float Analysis · Q3 FY 2025–2026 · 8 Active Projects

Portfolio Avg SPI
0.98
Slight delay
On Track
5 / 8
2 at risk · 1 critical
Critical Path Projects
2
ENG-003, ENG-006
Avg Total Float
33 days
Adequate schedule buffer
Filter:
Sort by:
ENG-003
Construction
Regional Water Treatment Upgrade
Baseline: Jun 2026→ Forecast: Nov 2026CRITICAL PATH
SPI
0.88
▼▼ Behind
CPI
0.91
▼ Over
Total Float
0d
No float
Sched. Var.
-120d
% Complete
85%
Critical
ENG-006
Design
Water Reclamation Plant Expansion
Baseline: Jun 2027→ Forecast: Sep 2027CRITICAL PATH
SPI
0.91
▼ Slight
CPI
0.94
▼ Over
Total Float
8d
Low
Sched. Var.
-75d
% Complete
42%
At Risk
ENG-001
Construction
Chino Basin Groundwater Recharge
Baseline: Dec 2026→ Forecast: Feb 2027
SPI
0.94
▼ Slight
CPI
0.97
▼ Over
Total Float
12d
Low
Sched. Var.
-45d
% Complete
62%
At Risk
ENG-007
Construction
Chino I Sewer Interceptor
Baseline: Sep 2027→ Forecast: Oct 2027
SPI
0.97
▼ Slight
CPI
0.98
▼ Over
Total Float
22d
Healthy
Sched. Var.
-18d
% Complete
35%
On Track
ENG-004
Design
Wastewater Biosolids Facility
Baseline: Mar 2028
SPI
1.00
▲ Ahead
CPI
0.99
▼ Over
Total Float
45d
Healthy
Sched. Var.
+0d
% Complete
28%
On Track
ENG-008
PDR
IEUA Admin Campus Solar
Baseline: Jun 2027
SPI
1.02
▲ Ahead
CPI
1.01
▲ Under
Total Float
60d
Healthy
Sched. Var.
+5d
% Complete
15%
On Track
ENG-002
Construction
Recycled Water Pipeline Expansion
Baseline: Sep 2026
SPI
1.03
▲ Ahead
CPI
1.01
▲ Under
Total Float
28d
Healthy
Sched. Var.
+5d
% Complete
78%
On Track
ENG-005
PDR
Inland Feeder Pipeline Rehab
Baseline: Dec 2029
SPI
1.05
▲ Ahead
CPI
1.02
▲ Under
Total Float
90d
Healthy
Sched. Var.
+10d
% Complete
8%
On Track