PMIS Implementation Roadmap
14-Month Implementation Plan · Total Investment: ~$610K · FY 2025–2027
Implementation Progress
Phase 2 of 6 In ProgressPh.1
Ph.2
Ph.3
Ph.4
Ph.5
Ph.6
Month 1Month 7Month 14+
1
Phase 1: Planning & Procurement
CompleteMonths 1–3
$85,000
Phase Budget
Key Deliverables
- Needs assessment & requirements document
- RFP package development & release
- Vendor evaluation & scoring
- Contract award & kick-off
Resource Allocation
PMO Director
25%
PMIS Project Manager
50%
IT/OT Integration Lead
15%
2
Phase 2: Configuration & Integration
In ProgressMonths 4–7
$320,000
Phase Budget
Key Deliverables
- System configuration & workflow setup
- SAP / Primavera P6 integration
- SharePoint document management link
- Data migration plan & execution
Resource Allocation
PMIS Project Manager
75%
IT/OT Integration Lead
50%
Business Process Analyst
50%
Vendor Implementation Team
100%
3
Phase 3: Testing & Validation
UpcomingMonths 8–9
$65,000
Phase Budget
Key Deliverables
- System Integration Test (SIT) execution
- User Acceptance Test (UAT) sign-off
- Performance & load testing
- SIT/UAT report & defect resolution
Resource Allocation
PMIS Project Manager
75%
Business Process Analyst
50%
Dept. Champions (2–3)
25%
Vendor Implementation Team
100%
4
Phase 4: Pilot Deployment
UpcomingMonths 10–11
$45,000
Phase Budget
Key Deliverables
- Pilot project selection & go-live
- Pilot assessment report
- Refined SOPs & user guides
- Pilot team training completion
Resource Allocation
PMIS Project Manager
75%
Dept. Champions (2–3)
25%
Vendor Implementation Team
100%
5
Phase 5: Full Go-Live & Hypercare
UpcomingMonths 12–13
$55,000
Phase Budget
Key Deliverables
- Agency-wide go-live
- All-staff training completion
- Hypercare support (30 days)
- Executive Power BI dashboard launch
Resource Allocation
PMO Director
25%
PMIS Project Manager
75%
Dept. Champions (2–3)
20%
Vendor Implementation Team
25%
6
Phase 6: Continuous Improvement
UpcomingMonth 14+
$40,000/yr
Phase Budget
Key Deliverables
- Enhancement backlog management
- Annual KPI review & recalibration
- User community of practice
- System optimization & upgrades
Resource Allocation
PMO Director
15%
PMIS Project Manager
50%
Total PMIS Implementation Investment
Includes vendor licensing, implementation services, internal labor, training, and contingency
~$610K
14-Month Total
$570K
Year 1 (Implementation)
$120K/yr
Year 2+ (Annual License)
$85K
Contingency (15%)